Construction Progress
Update: Fall 2026
Every day brings us one step closer to opening our new wing!
With 90% of the exterior work now complete, progress is increasingly visible inside the building as well.
Installation of the sprinkler system is underway, paving the way for the installation of the drop ceilings. Sheetrock is going up in all the classrooms, including specialized QuietRock soundproofing in the music classrooms to ensure optimal acoustics.
The benefits of this additional space will extend well beyond the new wing! Its opening will also allow us to repurpose other spaces throughout the existing building and create new opportunities for teachers and students.
More exciting updates on that soon!



Summer 2026 Update
Construction over the summer has been ongoing despite certain weather-related challenges. The building is now taking shape, and it is now easy to envision how this new wing will enhance programs and the overall student experience.
Here is an update on the work being currently done:
-
the masonry work on the first floor has been completed;
-
the roof has been completed;
-
stairs are being installed (the wing has three levels);
-
carpenters are working on enclosing the building and framing walls;
-
windows will be mounted soon;
-
steel is being delivered for the dining room opening;
-
plans are being drafted for the sprinkler system.
We are hoping for a November opening.
Stay tuned to see construction progress throughout the fall, and learn more about the Our School, Our Future campaign that brought this capital project to life here!